Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-15-37 04-0A7104 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 80% Location: Federal Project: 04-ALA-880-28.4/29.2 NHPA-8801(70) Progress payment No. 060 Payment period ending: 03-20-19 RGW CONSTRUCTION INC 6267 SOUTHFRONT RD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,857,797.87 1,297,805.16 2. a. Extra Work 5,853,278.49 -16,366.67 b. Adustment Comp. 670,513.85 0.00 3. Materials on Hand 245,260.74 -188,400.09 4. Earned Subject to Retention 53,626,850.95 1,093,038.40 5. Mobilization 5,080,000.00 0.00 6. Total Work Completed 58,461,590.21 7. Deductions -12,575.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,694,275.95 1,093,038.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,093,038.40