Dept. of Trans. PROGRESS Serial No. Contract No. 22-202-10-33 04-0A7714 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 58% Location: Federal Project: 04-ALA-80-6.4/6.6 ACIM-080-1(119) Progress payment No. 015 Payment period ending: 07-20-22 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,417,648.50 1,628,126.20 2. a. Extra Work 325,613.25 21,502.53 b. Adustment Comp. 3. Materials on Hand 72,943.52 -324,055.00 4. Earned Subject to Retention 13,816,205.27 1,325,573.73 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 15,743,261.75 7. Deductions -12,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,803,705.27 1,325,573.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,325,573.73