Dept. of Trans. PROGRESS Serial No. Contract No. 24-054-10-46 04-0A7724 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 57% Location: Federal Project: 04-ALA-80-6.4/6.8 ACIM-801(121) Progress payment No. 023 Payment period ending: 02-20-24 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,597,379.11 809,179.30 2. a. Extra Work 2,287,476.16 188,837.90 b. Adustment Comp. 3. Materials on Hand 292,906.14 0.00 4. Earned Subject to Retention 16,177,761.41 998,017.20 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 18,084,855.27 7. Deductions -11,280.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,366,481.41 998,017.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 998,017.20