Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-09-23 04-0A7724 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 66% Location: Federal Project: 04-ALA-80-6.4/6.8 ACIM-801(121) Progress payment No. 040 Payment period ending: 06-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,322,552.07 18,696.70 2. a. Extra Work 7,281,641.36 168,115.32 b. Adustment Comp. -153,153.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 29,451,040.43 186,812.02 5. Mobilization 2,200,000.00 0.00 6. Total Work Completed 31,651,040.43 7. Deductions -61,280.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,589,760.43 186,812.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,812.02