Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-07-55 04-0A8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 33% 04-ALA-13-4.2/4.9 Federal Project: 04-ALA-580-20.7/45.4 NONE 04-ALA-880-28.6/29.8 Progress payment No. 05 Payment period ending: 09-20-07 TRAFFIC SOLUTIONS INC 8490 HARTMEYER LANE REDDING CA 96002 Escrow No. 02295 Total Estimate This Estimate 1. Contract Itms Without Mobil. 248,630.00 15,750.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 248,630.00 15,750.00 5. Mobilization 157,500.00 0.00 6. Total Work Completed 406,130.00 7. Deductions -1,350.00 0.00 8. a.Contract Retentions -24,863.00 -1,575.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 379,917.00 14,175.00 10. Reduction Amt to Escrow 11. Payment to Escrow 24,860.00 12. Net Pymt. this Estimate 14,175.00