Dept. of Trans. PROGRESS Serial No. Contract No. 07-022-15-49 04-0A8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 23% 04-CC-4-4.7/12.8 Federal Project: 04-CC-24-0.4/2.1 NONE 04-CC-80-10.2/12.9 Progress payment No. 03 Payment period ending: 01-20-07 M BUMGARNER INC 1175 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,108.91 1,000.00 2.a. Extra Work 16,628.73 16,628.73 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 66,737.64 17,628.73 5. Mobilization 6. Total Work Completed 66,737.64 7. Deductions 8. a.Contract Retentions -6,673.76 -1,762.87 b. Unsatisfactory Prog. -0.01 0.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 60,063.87 15,865.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,865.86