Dept. of Trans. PROGRESS Serial No. Contract No. 07-059-09-52 04-0A8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 34% 04-CC-4-4.7/12.8 Federal Project: 04-CC-24-0.4/2.1 NONE 04-CC-80-10.2/12.9 Progress payment No. 04 Payment period ending: 02-20-07 M BUMGARNER INC 1175 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 231,608.91 181,500.00 2.a. Extra Work 17,998.11 1,369.38 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 249,607.02 182,869.38 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 324,607.02 7. Deductions 8. a.Contract Retentions -24,960.70 -18,286.94 b. Unsatisfactory Prog. 0.00 0.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 299,646.32 239,582.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 239,582.45