Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-08-45 04-0A9114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 95% 04-SON-1-0.0/58.5 Federal Project: 04-SON-12-9.6/16.1 ACHS-P907(35) 04-SON-116-0.5/35.0 STPG-P907(35) Progress payment No. 06 Payment period ending: 04-20-10 CENTRAL FENCE CO 148 OTTO CIRCLE SACRAMENTO CA 95822 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 819,152.75 77,037.50 2.a. Extra Work 11,380.29 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 830,533.04 77,037.50 5. Mobilization 32,500.00 0.00 6. Total Work Completed 863,033.04 7. Deductions -5,795.00 -915.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 857,238.04 76,122.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,122.50