Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-045-08-37 04-0AA494 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-ALA-80-0.0/2.7 NONE 04-ALA-580 Progress payment No. 004 Payment period ending: 02-06-20 HIGHWAY SPECIALTY COMPANY INC 6591 EASTSIDE RD REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,175.00 5,175.00 2. a. Extra Work 219,324.14 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 224,499.14 5,175.00 5. Mobilization 6. Total Work Completed 224,499.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 224,499.14 5,175.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,175.00