Dept. of Trans. PROGRESS Serial No. Contract No. 20-191-19-05 04-0AC904 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 37% Location: Federal Project: 04-ALA-24-5.9/6.2 NONE 04-CC-24-0.0/0.4 Progress payment No. 001 Payment period ending: 07-09-20 BENTANCOURT BROS CONSTRUCTION INC 8015 WEST 11TH ST TRACY CA 95304 9303 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 969,923.30 969,923.30 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 969,923.30 969,923.30 5. Mobilization 6. Total Work Completed 969,923.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 969,923.30 969,923.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 969,923.30