Dept. of Trans. PROGRESS Serial No. Contract No. 06-324-18-17 04-0C6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 65% 04-ALA-680-R12.4/R18.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 11-20-06 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02237 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,916,344.65 400,370.65 2.a. Extra Work 504.19 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 6,916,848.84 400,370.65 5. Mobilization 861,000.00 0.00 6. Total Work Completed 7,777,848.84 7. Deductions -125,400.00 8,000.00 8. a.Contract Retentions -345,842.44 -20,018.53 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,306,606.40 388,352.12 10. Reduction Amt to Escrow 11. Payment to Escrow 345,840.00 12. Net Pymt. this Estimate 388,352.12