Dept. of Trans. PROGRESS Serial No. Contract No. 02-023-16-07 04-0C7024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 67% 04-ALA-880-15.3/27.6 Federal Project: ACIM-880-1(46) Progress payment No. 11 Payment period ending: 01-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01740 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,430,865.41 383,832.27 2.a. Extra Work 91,804.83 19,805.07 b. Adjustment Comp. 43,130.04 -9,819.96 3. Materials on Hand 4. Earned Subject to Retention 10,565,800.28 393,817.38 5. Mobilization 2,074,230.00 0.00 6. Total Work Completed 12,640,030.28 7. Deductions -62,805.75 -710.53 8. a.Contract Retentions -528,290.01 -19,690.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,048,934.52 373,415.99 10. Reduction Amt to Escrow 11. Payment to Escrow 528,290.00 12. Net Pymt. this Estimate 373,415.99