Dept. of Trans. PROGRESS Serial No. Contract No. 02-171-15-03 04-0C7024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 73% 04-ALA-880-15.3/27.6 Federal Project: ACIM-880-1(46) Progress payment No. 16 Payment period ending: 06-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01740 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,254,093.16 453,084.70 2.a. Extra Work 131,914.01 6,159.18 b. Adjustment Comp. 57,734.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,443,741.92 459,243.88 5. Mobilization 2,183,400.00 0.00 6. Total Work Completed 14,627,141.92 7. Deductions -135,723.37 -85,883.68 8. a.Contract Retentions -622,187.10 -22,962.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,869,231.45 350,398.00 10. Reduction Amt to Escrow 11. Payment to Escrow 622,180.00 12. Net Pymt. this Estimate 350,398.00