Dept. of Trans. FINAL Serial No. Contract No. 03-288-11-03 04-0C7024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-880-15.3/27.6 Federal Project: ACIM-880-1(46) Progress payment No. 25 Payment period ending: 11-14-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01740 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,246,061.73 0.00 2.a. Extra Work 445,317.05 0.00 b. Adjustment Comp. 186,770.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 17,878,149.35 0.00 5. Mobilization 2,183,400.00 0.00 6. Total Work Completed 20,061,549.35 7. Deductions -23,923.39 0.00 8. a.Contract Retentions -853,038.96 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 853,038.96 0.00 9. Total pay to Contractor 20,037,625.96 0.00 10. Reduction Amt to Escrow -853,030.00 0.00 11. Payment to Escrow 853,030.00 12. Net Pymt. this Estimate 0.00