Dept. of Trans. PROGRESS Serial No. Contract No. 07-166-08-44 04-0C7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 36% 04-CC-4-R4.9/R16.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02279 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,638,417.45 1,164,176.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,638,417.45 1,164,176.80 5. Mobilization 988,000.00 208,000.00 6. Total Work Completed 3,626,417.45 7. Deductions -4,190.20 0.00 8. a.Contract Retentions -197,423.94 -49,999.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,424,803.31 1,322,176.93 10. Reduction Amt to Escrow 11. Payment to Escrow 197,420.00 12. Net Pymt. this Estimate 1,322,176.93