Dept. of Trans. PROGRESS Serial No. Contract No. 13-109-07-29 04-0C7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 96% 04-MRN-101-0.0/8.5 Federal Project: ACNH-Q101(211) Progress payment No. 13 Payment period ending: 04-20-13 GHILOTTI BROS INC 525 JACOBY STREET SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,181,297.91 -138,518.75 2.a. Extra Work 1,467,631.84 153,564.20 b. Adjustment Comp. 557,658.34 145,720.80 3. Materials on Hand 0.00 -22,386.10 4. Earned Subject to Retention 18,206,588.09 138,380.15 5. Mobilization 1,600,846.30 0.00 6. Total Work Completed 19,807,434.39 7. Deductions -21,600.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,785,834.39 138,380.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,380.15