Dept. of Trans. PROGRESS Serial No. Contract No. 07-202-08-02 04-0C8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 43% 04-SOL-505-R0.0/R10.6 Federal Project: NONE Progress payment No. 08 Payment period ending: 07-20-07 TEICHERT CONSTRUCTION P O BOX 1890 DAVIS CA 956171890 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,903,177.37 1,701,096.63 2.a. Extra Work 121,752.73 9,703.81 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,024,930.10 1,710,800.44 5. Mobilization 1,250,000.00 0.00 6. Total Work Completed 11,274,930.10 7. Deductions -10,500.00 0.00 8. a.Contract Retentions -501,246.51 -85,540.03 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,763,183.59 1,625,260.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,625,260.41