Dept. of Trans. PROGRESS Serial No. Contract No. 06-325-07-15 04-0C8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 66% 04-SCL-101-40.2/52.6 Federal Project: ACNH-Q101(105) Progress payment No. 08 Payment period ending: 11-20-06 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,013,834.31 1,511,962.04 2.a. Extra Work 17,087.09 613.88 b. Adjustment Comp. -9,550.54 -9,550.54 3. Materials on Hand 76,043.58 76,043.58 4. Earned Subject to Retention 11,097,414.44 1,579,068.96 5. Mobilization 985,000.00 0.00 6. Total Work Completed 12,006,370.86 7. Deductions -83,527.50 -2,400.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,998,886.94 1,576,668.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,576,668.96