Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-045-11-42 04-0C9504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-101-0.0/6.7 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-07-07 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,325,551.94 -318,816.00 2.a. Extra Work 24,807.73 19,582.28 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,350,359.67 -299,233.72 5. Mobilization 840,000.00 0.00 6. Total Work Completed 10,190,359.67 7. Deductions -20,150.00 0.00 8. a.Contract Retentions -482,479.67 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 482,479.67 482,479.67 9. Total pay to Contractor 10,170,209.67 183,245.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,245.95