Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-14-56 04-0C9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 64% 04-SM-280-10.8/R26.7 Federal Project: ACIM-280-1(111) Progress payment No. 12 Payment period ending: 02-20-08 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,641,413.57 456,902.71 2.a. Extra Work 154,882.23 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,796,295.80 456,902.71 5. Mobilization 1,920,000.00 0.00 6. Total Work Completed 14,716,295.80 7. Deductions -44,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,672,295.80 456,902.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,902.71