Dept. of Trans. FINAL Serial No. Contract No. 09-006-07-25 04-0E3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-1-40.7/47.7 Federal Project: 04-ALA-580-0.5/45.5 NONE 04-SM-35-26.1/31.5 Progress payment No. 05 Payment period ending: 10-23-08 MIDSTATE BARRIER INC P O BOX 30550 STOCKTON CA 952130550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 413,088.65 4,175.00 2.a. Extra Work 24,258.44 5,805.66 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 437,347.09 9,980.66 5. Mobilization 20,000.00 0.00 6. Total Work Completed 457,347.09 7. Deductions 8. a.Contract Retentions -20,426.07 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 20,426.07 0.00 9. Total pay to Contractor 457,347.09 9,980.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,980.66