Dept. of Trans. FINAL Serial No. Contract No. 10-118-11-45 04-0E3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-1-19.9/25.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 11-12-09 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02422 Total Estimate This Estimate 1. Contract Itms Without Mobil. 932,624.57 0.00 2.a. Extra Work 88,024.51 0.00 b. Adjustment Comp. -7,568.66 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,013,080.42 0.00 5. Mobilization 6. Total Work Completed 1,013,080.42 7. Deductions 8. a.Contract Retentions -50,104.90 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 50,104.90 0.00 9. Total pay to Contractor 1,013,080.42 0.00 10. Reduction Amt to Escrow -50,100.00 0.00 11. Payment to Escrow 50,100.00 12. Net Pymt. this Estimate 0.00