Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-274-10-43 04-0E4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-112-R0.0/1.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-18-08 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 487,135.20 81,683.00 2.a. Extra Work 5,881.21 5,881.21 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 493,016.41 87,564.21 5. Mobilization 6. Total Work Completed 493,016.41 7. Deductions 8. a.Contract Retentions -20,272.61 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 20,272.61 20,272.61 9. Total pay to Contractor 493,016.41 107,836.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,836.82