Dept. of Trans. FINAL Serial No. Contract No. 09-027-14-33 04-0E4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-112-R0.0/1.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-18-08 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 507,442.80 20,307.60 2.a. Extra Work 8,294.79 2,413.58 b. Adjustment Comp. -6,306.97 -6,306.97 3. Materials on Hand 4. Earned Subject to Retention 509,430.62 16,414.21 5. Mobilization 6. Total Work Completed 509,430.62 7. Deductions 8. a.Contract Retentions -20,272.61 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 20,272.61 0.00 9. Total pay to Contractor 509,430.62 16,414.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,414.21