Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-362-12-13 04-0E5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-380-4.7/6.4 Federal Project: NONE Progress payment No. 08 Payment period ending: 12-16-09 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 597,458.11 3,915.50 2.a. Extra Work 9,805.39 7,787.00 b. Adjustment Comp. 63,184.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 670,447.50 11,702.50 5. Mobilization 53,000.00 0.00 6. Total Work Completed 723,447.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 723,447.50 11,702.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,702.50