Dept. of Trans. PROGRESS Serial No. Contract No. 08-355-07-51 04-0E5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 15% 04-SCL-85-0.3/ .0 Federal Project: 04-SCL-87-3.4/9.2 NONE 04-SCL-280-R2.5/ .0 Progress payment No. 03 Payment period ending: 12-20-08 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 520,957.70 138,763.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 118,730.00 118,730.00 4. Earned Subject to Retention 639,687.70 257,493.50 5. Mobilization 104,500.00 0.00 6. Total Work Completed 625,457.70 7. Deductions 8. a.Contract Retentions -32,682.73 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 711,504.97 257,493.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,493.50