Dept. of Trans. PROGRESS Serial No. Contract No. 08-355-07-56 04-0E8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 48% 04-CC-80-2.8/4.1 Federal Project: 04-CC-680-R4.2/R17.4 NONE 04-CC-24-1.2/R6.0 Progress payment No. 04 Payment period ending: 12-20-08 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVENUE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 955,702.06 212,962.66 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 955,702.06 212,962.66 5. Mobilization 80,000.00 0.00 6. Total Work Completed 1,035,702.06 7. Deductions -5,000.00 0.00 8. a.Contract Retentions -47,785.10 -10,648.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 982,916.96 202,314.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,314.53