Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-07-53 04-0E8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 33% 04-SCL-35-7.7/14.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-08 ALANIZ CONSTRUCTION INC 7100 STEVENSON BOULEVARD FREMONT CA 94538 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 321,800.00 321,800.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 321,800.00 321,800.00 5. Mobilization 6. Total Work Completed 321,800.00 7. Deductions 8. a.Contract Retentions -16,090.00 -16,090.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 305,710.00 305,710.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 305,710.00