Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-09-22 04-0E9304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 77% 04-ALA-580-R40.3/46.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-09 BAY LINE CUTTING AND CORING INC 1033 YERBA BUENA AVENUE OAKLAND CA 94608 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 451,612.18 451,612.18 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,612.18 451,612.18 5. Mobilization 34,000.00 34,000.00 6. Total Work Completed 485,612.18 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 485,612.18 485,612.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 485,612.18