Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-11-14 04-0E9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 99% 04-SON-1-19.7/ .0 Federal Project: 04-SON-12-R15.6/29.4 NONE 04-SON-101-21.7/37.0 Progress payment No. 07 Payment period ending: 06-20-11 VICTORY ENGINEERS INC 575 E ALLUVIAL AVE SUITE 106 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 318,825.79 42,063.97 2.a. Extra Work 41,605.77 0.00 b. Adjustment Comp. 2,688.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 363,120.37 42,063.97 5. Mobilization 35,178.49 0.00 6. Total Work Completed 398,298.86 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 398,298.86 42,063.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,063.97