Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-09-52 04-0G2214 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 100% Location: Federal Project: 04-ALA-13-7.2/7.2 NONE 04-CC-680-11.2/11.2 Progress payment No. 005 Payment period ending: 08-20-19 GRUENDL INC DBA RAY'S ELECTRIC 411 PENDLETON WAY #B OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 535,041.26 204,969.26 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 535,041.26 204,969.26 5. Mobilization 35,000.00 0.00 6. Total Work Completed 570,041.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 570,041.26 204,969.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 204,969.26