Dept. of Trans. PROGRESS Serial No. Contract No. 17-080-11-03 04-0G7204 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 49% Location: Federal Project: 04-SCL-152-11.9/11.9 HSNH P-P152(87) Progress payment No. 006 Payment period ending: 03-20-17 BAY CITIES PAVING& GRADING INC 1450 CIVIC CT BLDG B #400 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 963,592.22 94,500.00 2. a. Extra Work 119,499.40 15,109.85 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,083,091.62 109,609.85 5. Mobilization 215,000.00 0.00 6. Total Work Completed 1,298,091.62 7. Deductions -49,374.07 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,248,717.55 109,609.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 109,609.85