Dept. of Trans. PROGRESS Serial No. Contract No. 23-319-09-51 04-0J3004 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 41% Location: Federal Project: 04-SON-1-26.7/27.1 ACST-P001(679) Progress payment No. 014 Payment period ending: 11-20-23 ARGONAUT CONSTRUCTORS PO BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,491,149.45 828,181.80 2. a. Extra Work 505,020.02 48,961.57 b. Adustment Comp. 3. Materials on Hand 46,218.00 -56,136.00 4. Earned Subject to Retention 11,042,387.47 821,007.37 5. Mobilization 534,895.00 0.00 6. Total Work Completed 11,531,064.47 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,577,282.47 821,007.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 821,007.37