Dept. of Trans. PROGRESS Serial No. Contract No. 22-077-14-35 04-0J4704 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 15% Location: Federal Project: 04-ALA-13-8.4/12.6 SNHG-000C(524) 04-ALA-61-19.3/21.9 04-CC-123-0.6/0.6 Progress payment No. 001 Payment period ending: 03-20-22 ST FRANCIS ELECTRIC INC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,022.50 221,022.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 221,022.50 221,022.50 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 296,022.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 296,022.50 296,022.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 296,022.50