Dept. of Trans. PROGRESS Serial No. Contract No. 24-233-10-37 04-0J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 80% Location: Federal Project: 04-CC-4-L0.1/R20.4 SNHG-P004(160) Progress payment No. 012 Payment period ending: 08-20-24 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,525,601.49 664,536.10 2. a. Extra Work 944,877.92 186,244.03 b. Adustment Comp. 3. Materials on Hand 127,386.00 -148,517.00 4. Earned Subject to Retention 11,597,865.41 702,263.13 5. Mobilization 595,000.00 0.00 6. Total Work Completed 12,065,479.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,192,865.41 702,263.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 702,263.13