Dept. of Trans. PROGRESS Serial No. Contract No. 24-260-14-12 04-0J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 88% Location: Federal Project: 04-CC-4-L0.1/R20.4 SNHG-P004(160) Progress payment No. 013 Payment period ending: 09-20-24 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,368,531.66 842,930.18 2. a. Extra Work 1,069,754.43 124,876.51 b. Adustment Comp. 3. Materials on Hand 106,608.00 -20,778.00 4. Earned Subject to Retention 12,544,894.09 947,028.69 5. Mobilization 595,000.00 0.00 6. Total Work Completed 13,033,286.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,139,894.09 947,028.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 947,028.69