Dept. of Trans. PROGRESS Serial No. Contract No. 24-292-21-13 04-0J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 95% Location: Federal Project: 04-CC-4-L0.1/R20.4 SNHG-P004(160) Progress payment No. 014 Payment period ending: 10-20-24 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,005,664.22 2,637,132.56 2. a. Extra Work 1,091,871.97 22,117.54 b. Adustment Comp. 3. Materials on Hand 81,848.00 -24,760.00 4. Earned Subject to Retention 15,179,384.19 2,634,490.10 5. Mobilization 595,000.00 0.00 6. Total Work Completed 15,692,536.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,774,384.19 2,634,490.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,634,490.10