Dept. of Trans. PROGRESS Serial No. Contract No. 22-078-06-13 04-0J5604 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 56% Location: Federal Project: 04-SCL-101-0.0/4.2 ACNH-X085(63) 04-SCL-237-2.4 Progress payment No. 009 Payment period ending: 03-20-22 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,941,520.98 316,304.35 2. a. Extra Work 21,569.08 7,446.56 b. Adustment Comp. 3. Materials on Hand 639,352.00 159,901.00 4. Earned Subject to Retention 2,602,442.06 483,651.91 5. Mobilization 636,500.00 0.00 6. Total Work Completed 2,599,590.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,238,942.06 483,651.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 483,651.91