Dept. of Trans. PROGRESS Serial No. Contract No. 18-022-09-14 04-0J6404 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 43% Location: Federal Project: 04-SON-101-29.3/R43.4 ACNH-Q101(307) Progress payment No. 008 Payment period ending: 01-20-18 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,994,824.64 99,634.73 2. a. Extra Work 257,057.95 24,333.21 b. Adustment Comp. 109,678.00 0.00 3. Materials on Hand 1,367,292.71 1,367,292.71 4. Earned Subject to Retention 24,728,853.30 1,491,260.65 5. Mobilization 4,968,500.00 0.00 6. Total Work Completed 28,330,060.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,697,353.30 1,491,260.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,491,260.65