Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-14-48 04-0J6404 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 45% Location: Federal Project: 04-SON-101-29.3/R43.4 ACNH-Q101(307) Progress payment No. 009 Payment period ending: 02-20-18 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,293,242.49 1,298,417.85 2. a. Extra Work 390,561.06 133,503.11 b. Adustment Comp. 109,678.00 0.00 3. Materials on Hand 865,406.55 -501,886.16 4. Earned Subject to Retention 25,658,888.10 930,034.80 5. Mobilization 5,230,000.00 261,500.00 6. Total Work Completed 30,023,481.55 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,888,888.10 1,191,534.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,191,534.80