Dept. of Trans. PROGRESS Serial No. Contract No. 18-141-16-23 04-0J6404 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 44% Location: Federal Project: 04-SON-101-29.3/R43.4 ACNH-Q101(307) Progress payment No. 012 Payment period ending: 05-20-18 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,849,973.41 2,727,408.02 2. a. Extra Work 537,859.74 95,303.94 b. Adustment Comp. 168,809.50 10,000.00 3. Materials on Hand 324,444.13 129,513.00 4. Earned Subject to Retention 30,881,086.78 2,962,224.96 5. Mobilization 5,230,000.00 0.00 6. Total Work Completed 35,786,642.65 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 36,106,086.78 2,962,224.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,962,224.96