Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-14-19 04-0J6404 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 57% Location: Federal Project: 04-SON-101-29.3/R43.4 ACNH-Q101(307) Progress payment No. 013 Payment period ending: 06-20-18 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,986,265.69 7,136,292.28 2. a. Extra Work 582,479.09 44,619.35 b. Adustment Comp. 168,809.50 0.00 3. Materials on Hand 87,983.13 -236,461.00 4. Earned Subject to Retention 37,825,537.41 6,944,450.63 5. Mobilization 5,230,000.00 0.00 6. Total Work Completed 42,967,554.28 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,050,537.41 6,944,450.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,944,450.63