Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-15-18 04-0J6404 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 89% Location: Federal Project: 04-SON-101-29.3/R43.4 ACNH-Q101(307) Progress payment No. 019 Payment period ending: 11-20-18 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,531,678.31 29,821.70 2. a. Extra Work 1,400,737.95 526,329.37 b. Adustment Comp. 1,159,307.33 85,406.05 3. Materials on Hand 4. Earned Subject to Retention 49,091,723.59 641,557.12 5. Mobilization 5,230,000.00 0.00 6. Total Work Completed 54,321,723.59 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 54,306,723.59 641,557.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 641,557.12