Dept. of Trans. PROGRESS Serial No. Contract No. 20-237-11-16 04-0J6424 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 17% Location: Federal Project: 04-SON-101-32.8/R54.2 NONE Progress payment No. 007 Payment period ending: 08-20-20 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,792,819.85 4,122,627.49 2. a. Extra Work 4,260.16 4,260.16 b. Adustment Comp. 2,047,599.37 0.00 3. Materials on Hand 337,981.60 -280,263.52 4. Earned Subject to Retention 26,182,660.98 3,846,624.13 5. Mobilization 3,301,250.00 0.00 6. Total Work Completed 29,145,929.38 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,483,910.98 3,846,624.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,846,624.13