Dept. of Trans. PROGRESS Serial No. Contract No. 20-295-16-02 04-0J6424 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 24% Location: Federal Project: 04-SON-101-32.8/R54.2 NONE Progress payment No. 009 Payment period ending: 10-20-20 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,877,474.51 6,149,629.17 2. a. Extra Work 887,551.47 862,768.98 b. Adustment Comp. 630,173.59 -1,417,425.78 3. Materials on Hand 274,795.15 274,795.15 4. Earned Subject to Retention 34,669,994.72 5,869,767.52 5. Mobilization 3,475,000.00 0.00 6. Total Work Completed 37,870,199.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,144,994.72 5,869,767.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,869,767.52