Dept. of Trans. PROGRESS Serial No. Contract No. 21-295-11-47 04-0J6424 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 43% Location: Federal Project: 04-SON-101-32.8/R54.2 NONE Progress payment No. 021 Payment period ending: 10-20-21 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,871,636.95 2,636,351.52 2. a. Extra Work 1,345,660.91 0.00 b. Adustment Comp. 535,836.95 0.00 3. Materials on Hand 4. Earned Subject to Retention 47,753,134.81 2,636,351.52 5. Mobilization 3,475,000.00 0.00 6. Total Work Completed 51,228,134.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,228,134.81 2,636,351.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,636,351.52