Dept. of Trans. PROGRESS Serial No. Contract No. 22-021-16-16 04-0J7104 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 41% Location: Federal Project: 04-SOL-80-1.8/4.4 NONE Progress payment No. 018 Payment period ending: 01-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,352,518.29 309,755.00 2. a. Extra Work 244,360.22 43,348.87 b. Adustment Comp. 872,384.27 218,582.29 3. Materials on Hand 43,623.15 0.00 4. Earned Subject to Retention 10,512,885.93 571,686.16 5. Mobilization 1,900,000.00 0.00 6. Total Work Completed 12,369,262.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,412,885.93 571,686.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 571,686.16