Dept. of Trans. PROGRESS Serial No. Contract No. 22-263-09-41 04-0J7104 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 64% Location: Federal Project: 04-SOL-80-1.8/4.4 NONE Progress payment No. 027 Payment period ending: 09-20-22 BROSAMER & WALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,912,327.47 675,378.80 2. a. Extra Work 965,463.85 17,398.90 b. Adustment Comp. 1,996,890.56 456,556.68 3. Materials on Hand 4. Earned Subject to Retention 19,874,681.88 1,149,334.38 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 21,874,681.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,874,681.88 1,149,334.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,149,334.38