Dept. of Trans. PROGRESS Serial No. Contract No. 20-260-10-59 04-0J7204 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 14% Location: Federal Project: 04-SM-84-9.4/10.0 ACNH-P081(33) 04-SM-280-7.0/7.7 Progress payment No. 001 Payment period ending: 09-20-20 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 145,450.00 145,450.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 145,450.00 145,450.00 5. Mobilization 86,250.00 86,250.00 6. Total Work Completed 231,700.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 231,700.00 231,700.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,700.00