Dept. of Trans. PROGRESS Serial No. Contract No. 24-017-18-43 04-0K0704 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 74% Location: Federal Project: 04-SM-1-26.4/32.9 CSTG-X081(35) 04-SM-35-24.3/30.8 04-SM-82-0.8/25.1 Progress payment No. 012 Payment period ending: 01-20-24 ST FRANCIS ELECTRIC LLC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,004,067.80 72,332.50 2. a. Extra Work 424,995.68 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,429,063.48 72,332.50 5. Mobilization 600,000.00 0.00 6. Total Work Completed 5,029,063.48 7. Deductions -17,800.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,011,263.48 72,332.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,332.50